Horizon Europe · NEB Facility · IA · lump sum
Horizon Europe NEB: innovative solutions for the sustainable and beautiful use of vertical space. An Innovation Action (TRL 6–8) for consortia that add homes or green space above buildings
About €5 million per project to demonstrate solutions that use unused vertical space for housing or green space. Deadline 1 December 2026, 17:00 Brussels time.
Status: Closing soon · Deadline: 1 Dec 2026, 17:00 Brussels time
- €5 million — expected EU contribution
- €15 million — topic budget, about 3 projects
- TRL 6–8 — expected at the project end
Call facts
- Grant: Around €5 million per project; other amounts allowed
- Funding: Lump sum; rate up to 70%, non-profits up to 100%
- Who: Any legal entity, in a consortium
- Where: EU Member States, associated countries, OCTs
- Partners: 3+ independent entities, 3 countries, 1+ in the EU
- TRL: Any start TRL; TRL 6–8 expected at the end
- Duration: Not fixed by the topic
- Effort: High
HORIZON-NEB-2026-01-REGEN-03 · WP 2026–2027 · run by CINEA
At a glance
A good fit only for a consortium that already has a nearly complete proposal and a tested solution for unused vertical space, a community ready to co-create and a site to demonstrate it; the deadline is 1 December 2026, 17:00 Brussels time (18:00 in Romania).
- What it funds: developing and demonstrating at least one innovative solution that uses unused or under-used vertical space above buildings and/or streets, for example rooftop community gardens, urban vertical farming or vertical extensions, to improve the availability and affordability of housing and/or provide green space. It integrates circularity, assesses life-cycle environmental, social and economic impacts, limits the harm of densification, assesses reduced demand for land and tackles regulatory, technical and societal barriers. Activities may start at any TRL and are expected to reach TRL 6–8.
- Money: €15 million for around 3 projects, about €5 million each, paid as a lump sum fixed from a detailed budget table. The funding rate is up to 70% (up to 100% for non-profit legal entities) and is already applied inside the lump sum.
- Who can apply: any legal entity, in a consortium of three independent entities from three countries, one of them in an EU Member State. Romanian entities are eligible. Entities established in China cannot take part, although the text encourages international cooperation. The topic text requires the effective contribution of social sciences and humanities (SSH) disciplines and the involvement of SSH experts; building-sector professionals must take part where the work concerns the built environment.
- Who can still use this deadline: a consortium with a written proposal that needs a last check of the rules, or a partner joining in the last days (it needs an EU Login account, a PIC, a place in Part A and a line in the budget table). A team starting from zero should prepare for the next round instead.
- Next round: HORIZON-NEB-2027-01 is planned to open on 5 May 2027 with a deadline of 1 December 2027, 17:00 Brussels time. It has no vertical-space topic. The joint call HORIZON-NEB-2027-02 with the Soil Deal for Europe Mission (deadline 15 September 2027) has one Innovation Action on reducing soil sealing through urban and territorial design (TRL 6–8, about €7.5 million per project). A repeat of this topic is not published; further 2027 call documents are not published.
Key dates
- 5 May 2026 — Call opened
- 1 Dec 2026 — Deadline, 17:00 Brussels (18:00 Romania)
- May 2027 — Results (indicative, about 5 months on)
- 5 May 2027 — Next round opens (planned, 2027-01)
- Aug 2027 — Grant signature (indicative, about 8 months on)
- 1 Dec 2027 — Next round deadline (planned, 2027-01)
Is it for you?
Good fit
- A consortium with a nearly complete proposal, a demonstration site and permit route, and partners in three countries
- Rooftop-farming, urban-agriculture, greening, timber and lightweight-structure firms ready for TRL 6–8 demonstration
- Housing providers and municipalities that want to add homes or green space without new land
- Architects and urban planners who can design vertical extensions and multifunctional structures
- Community groups, cultural and creative organisations and SSH researchers for co-creation and acceptance
Not a fit
- Single organisations or consortia from fewer than three countries
- Teams with no draft and no site yet: the deadline is too close, so prepare for the next round
- Projects that build on open land: the topic is about unused vertical space above buildings and streets
- Proposals that ignore densification, regulation or community acceptance, which the text names as risks
- Consortia that rely on entities established in China in any capacity, subcontractors included
Eligibility checklist
- At least three independent legal entities as beneficiaries, each in a different country: one in an EU Member State, the other two in Member States or Horizon Europe associated countries. Affiliated entities do not count towards the minimum (General Annex B, p. 13).
- Solution: at least one innovative solution that makes use of un-used or under-used vertical space above buildings and/or streets in a beautiful and sustainable manner to improve the availability and affordability of housing and/or provide more green spaces (Part 13, p. 51). The text names urban vertical farming, community gardens on rooftops, vertical extensions and other multifunctional structures as suitable examples.
- What the proposal must also do: integrate circularity principles; assess life-cycle environmental, social and economic impacts with appropriate methods; if relevant, minimise and mitigate the negative effects of densification; assess the potential to reduce demand for land use; identify and address regulatory, technical and societal barriers.
- People: a participatory and transdisciplinary approach that involves the local community and, if relevant, cultural and creative industries in the co-creation of the solution. To the extent possible, proposals contribute to the urban greening goals of the Nature Restoration Regulation.
- TRL: activities may start at any level and are expected to reach TRL 6–8 by the end (TRL 6: technology demonstrated in a relevant environment; TRL 8: system complete and qualified; General Annex B, p. 15).
- International cooperation is encouraged by the text. Any legal entity may take part, but only entities in the countries listed in General Annex B are eligible for funding; others can join as associated partners without costs. Entities established in China are barred in this Innovation Action.
- Where a proposal works on the built environment (design, construction, renovation), the Work Programme requires the participation of relevant key building-sector professionals, such as architects, urban planners and landscape designers (Part 13, pp. 6–7).
- SSH: the topic text says it “requires the effective contribution of social sciences and humanities (SSH) disciplines and the involvement of SSH experts, institutions as well as the inclusion of relevant SSH expertise, in order to produce meaningful and significant effects enhancing the societal impact of the related research activities” (Part 13, p. 52).
- NEB hub: the topic text says “Proposals are expected to allocate at least 0.8% of their budget for engaging with the Horizon Europe-funded 'New European Bauhaus hub for results and impact' to share their intermediate and final results, findings and learning, as well as to contribute to impact assessment” (Part 13, p. 52). Portal answer 102435 adds that the percentage is calculated on the total budget of the project and that there are no specific budget categories or cost headings where these expenses should be allocated.
- Entities established in China cannot take part in any Innovation Action, in any capacity: as beneficiaries, affiliated entities, associated partners, third parties giving in-kind contributions or subcontractors. For this destination the Work Programme says so in terms for both RIAs and IAs (Part 13, p. 45; General Annexes, Annex B, pp. 6–7). Exceptions may be granted case by case for justified reasons. Chinese universities under the Ministry of Industry and Information Technology are excluded from every action.
- Public bodies, research organisations and higher education establishments (private ones included) from Member States and associated countries that take part as beneficiaries or affiliated entities need a gender equality plan at the moment of grant signature and during the grant. It must cover four minimum process requirements: publication, dedicated resources, data collection and monitoring, and training (General Annex B, p. 17).
- Every participant needs a PIC to submit: beneficiaries, affiliated entities and associated partners. Beneficiaries and affiliated entities are validated at grant preparation; associated partners are not (General Annexes, p. 36).
- Exclusions: entities under EU restrictive measures cannot take part in any capacity, and neither can entities established in Russia, Belarus or non-government controlled territories of Ukraine (exceptions may be granted case by case for justified reasons), nor entities established outside Russia that are directly or indirectly owned for more than 50% by an entity established in Russia (General Annex B, p. 10).
Our take
- Add space without new land: the topic responds to the clash between housing demand and nature and biodiversity in neighbourhoods by using space above existing buildings and streets.
- Housing or green, or both: a solution may deliver more affordable housing, more green space, or both, which fits architecture, greening and urban-farming firms alike.
- A warning built in: the text itself names the risks (social acceptance, regulation, excessive densification, environmental risks), so a proposal that shows how it manages them reads stronger.
- The largest budget in its destination: €15 million for around 3 projects, so about three projects are expected in this topic.
- Lump sum with a catch for companies: the rate is up to 70%, and up to 100% for non-profit legal entities, applied inside the lump sum.
How to win
- If your proposal is already written, use the remaining time for a rules check: at least one solution above buildings and/or streets; housing and/or green space as the result; circularity; life-cycle assessment; densification effects; land-use reduction; regulatory, technical and societal barriers; community co-creation; the SSH contribution the topic text asks for; TRL 6–8 at the end; at least 0.8% of the budget planned for the NEB hub (expected by the topic); at most 45 pages; a detailed budget table saved as .xlsx. Each submission replaces the previous one, so submit early: the Online Manual advises submitting “as early as possible and at least 48 hours before the deadline” (Online Manual, PDF p. 38). Derived estimate: 48 hours before 1 December 2026, 17:00 Brussels time is Sunday 29 November 2026, 17:00. After the deadline nothing can be corrected, and the General Annexes say deadlines cannot be extended at an applicant's request. A Portal notice of 26 October 2026 says Part A of proposals was moved to a new technology: anyone editing a draft or a submitted proposal should check Part A again, because some data may need to be entered again.
- If a partner is joining late — for example a municipality or building owner that offers the demonstration site, or a community or cultural organisation that leads the co-creation — it needs an EU Login account and a PIC, a place in Part A and a line in the detailed budget table. The Portal's Partner Search lists organisations looking for a consortium. Public bodies, research organisations and universities from Member States and associated countries must have a gender equality plan at grant signature and during the grant.
- If you are starting from zero, do not rush this deadline. HORIZON-NEB-2027-01 (planned opening 5 May 2027, deadline 1 December 2027) has no vertical-space topic, and a repeat is not published. The joint call HORIZON-NEB-2027-02 (deadline 15 September 2027) has an Innovation Action on reducing soil sealing through urban and territorial design, which is related by subject, but its call documents are not published. Use the months before to secure sites and permits, and to build the consortium.
- Secure the demonstration site and its permits first. Structures above buildings and streets raise planning, structural and ownership questions that decide whether a demonstration is possible.
- Put effort into the Impact section: for Innovation Actions its score counts 1.5 times in the ranking (General Annex D, p. 26). For proposals with equal scores the tie-break runs in this order (General Annex F, p. 28): first, proposals that address aspects of the call not covered by more highly ranked proposals have the highest priority; then those proposals are ranked by their Impact score and then their Excellence score; then gender balance among the researchers with a leading role; then geographical diversity (the number of Member States or Associated Countries in the proposal not otherwise receiving funds from projects higher up the ranking list, then budget if equal); last, other factors such as synergies between projects or the involvement of SMEs. Show the number of homes or the area of green space created and who will replicate the solution.
- Plan co-financing from the start: non-profit legal entities can be funded up to 100%, for-profit partners up to 70%.
Documents to prepare
- Part A (online) and Part B (PDF, at most 45 pages for the title, participants list and sections 1 to 3) in the Funding & Tenders Portal submission system; the Portal form is used, not the standard template
- The detailed budget table (HE LS, Excel): saved as .xlsx for upload, work packages in the same order as in Part B, beneficiaries in the same order as Part A; it fixes the lump sum, and ineligible costs in it can reduce the grant, even later
- A PIC for every participant (beneficiaries, affiliated entities and associated partners), and an EU Login account for each contact person; a partner joining late must be in the Participant Register first
- A work plan with the vertical-space solution, the demonstration site and permit route, the circularity approach, the life-cycle assessment, community co-creation and the contribution of SSH disciplines and experts
- A plan to manage densification effects and regulatory barriers, with the plan for exploitation and dissemination that every application needs
- Resources for engaging with the NEB hub for results and impact: the topic expects at least 0.8% of the budget, calculated on the total project budget (no fixed cost heading; Portal answer 102435)
- A gender equality plan for public bodies, research organisations and higher education establishments from Member States and associated countries that take part as beneficiaries or affiliated entities, valid at grant signature and during the grant
- After selection: legal entity validation (beneficiaries and affiliated entities), a financial capacity check (normally of the coordinator if the requested grant is EUR 500,000 or more; not for public bodies, international organisations or low-value grants of EUR 60,000 or less; possible for other participants if needed), a declaration of honour from each participant and a consortium agreement
Risks to weigh
- Site and permits: structures above buildings or streets need planning, structural and ownership consent. A site lost late breaks the demonstration.
- Acceptance and densification: the text warns of social acceptance problems, regulatory barriers and excessive densification, and asks for mitigation. An unaddressed risk weakens the Impact case.
- Evidence: life-cycle environmental, social and economic impacts and the effect on land-use demand have to be assessed with appropriate methods, not only claimed.
- Competition: around 3 projects are expected for this topic. No applicant figures are published for this call; for the previous round the Commission's info-day slide shows 367 proposals for 25 expected projects (6.8%) across 11 topics.
- Time: the deadline is 1 December 2026, 17:00 Brussels time. It cannot be extended at an applicant's request, and no corrections or resubmissions are possible afterwards. Pages beyond 45 are made invisible.
- China: entities established in China are not eligible in any capacity, subcontractors and in-kind third parties included (exceptions may be granted case by case for justified reasons). This applies although international cooperation is encouraged.
- Lump sum: payment follows completed work packages, so an incomplete work package is not paid until it is completed. The budget table fixes the amount, and ineligible costs in it can reduce the grant, even after the project has ended.
- Dates can move: the Director-General may delay the deadline by up to two months for everyone, and the evaluation and signature dates are only indicative (about 5 and about 8 months after the deadline). Do not plan on a delay.
Official documents
- Official call page
- Where to apply
- Guidelines
- Templates / documents
- Work Programme
- Additional documents
- Full analysis (PDF)
Based on the Horizon Europe Work Programme 2026–2027, Part 13 New European Bauhaus Facility (Decision C(2026) 6687/2 of 29 September 2026, topic text pp. 50–52) and Part 15 General Annexes, the Funding & Tenders Portal topic data and page for HORIZON-NEB-2026-01-REGEN-03 (published 12 December 2025), the standard application form V5.1 (22 January 2026), the lump-sum model grant agreement V1.0 (1 November 2024), the detailed budget table V3.6, the Online Manual V1.3 (1 May 2026) and the Portal answer 102435, checked on 20 November 2026. Official updates prevail. Image: EUnita.